Project Management English: How to Tell Clients About Schedule Slips
Published October 6, 2026
Know Exactly What to Say
The full script is below, word for word, for when the schedule slips and the client needs to hear it from you. Copy it, change the names and dates, and it is ready to send or say.
Practice It Before the Real Conversation

A printable PDF. Say the lines out loud, then fill in your own project's names and dates, so the words are yours before the client is on the line.
Download the practice sheet (PDF)How to Use a Script
Four steps:
- Watch the video once.
- Copy the script. Change the names, dates, and numbers to match your project.
- Say it out loud until it sounds like you. Use the practice sheet if the page has one.
- Use it in the real conversation, in the email or on the call.
The Script
Word for word, as said in the video. Copy it and change the names, dates, and numbers to match your project.
ScriptProject Management English: How to Tell Clients About Schedule Slips
Your client needs to hear this from you first. Told early, a delay is an update. If the client finds out after the permit date slips, the same news sounds like an excuse. You'll have one short email that tells the client early, gives your recommendation, and asks for their answer by a date.
On the call, you confirmed the firm has everything it needs from your team. You also have the firm's new delivery date. So the open question is the permit package. You recommend, and the client weighs in.
The email has four parts. 1. Facts. 2. Options. 3. Recommendation. 4. Next step. First, the whole email.
On today's coordination call, our structural engineering firm told us the structural submittal will be three days late, due to time allocated to an additional independent check of the calculations. Accurate calculations protect the whole project, and we can likely recover the three days elsewhere in the permitting process. We can submit the permit package Thursday as planned without the structural sheets, or hold it and submit the complete package next Tuesday. I recommend holding it, because an incomplete package usually brings agency comment rounds and resubmittal fees, and each review can take a month or more. Please let me know which you prefer by Wednesday, so we have time to prepare Thursday's submittal if you choose that option. If I have not heard from you by then, I will hold the package and submit the complete package next Tuesday. Going forward, our team and the firm are building this additional check into the schedule for every remaining structural submittal.
Now the four lines that do the work.
Facts. Due to time allocated to an additional independent check of the calculations. You give the delay and its reason in the same sentence, in plain words. The next sentence says what the check protects, so the client sees the check as quality control. The firm is named, and it isn't blamed. You could also say, because the firm added an independent check. Or, to allow time for an additional check.
Options. Submit the permit package Thursday as planned without the structural sheets, or hold it and submit the complete package next Tuesday. Each option has a date, so the client can see the schedule impact of each choice. Either one is a real choice for the client.
Recommendation. I recommend holding it, because an incomplete package usually brings agency comment rounds and resubmittal fees. Say I recommend, and give the reason in the same sentence. The reason is how agency review works, so it's a fact the client can check. Holding costs a few days. Submitting early can cost months. You could also say, my recommendation is to hold it. Or, I suggest we submit the complete package.
Next step. Please let me know which you prefer by Wednesday, so we have time to prepare Thursday's submittal. The deadline comes with its reason, so Wednesday makes sense to the client. The client weighs in on your schedule decision, and you keep control of the schedule. This deadline is real, so you say what you'll do if you don't hear back. It must be the option you recommended. When there is more time, leave that sentence out. You could also say, could you confirm your choice by Wednesday, so we can plan the submittal?
The last sentence tells the client what changes. Both teams are building the check into the schedule, so it doesn't cause another delay.
Now let's practice. Practice 1 is slow. Repeat after me.
Each button opens the video at that round, slow, normal business pace, or full business speed. The line is the same every time; only the pace changes.
- On today's coordination call, our structural engineering firm told us the structural submittal will be three days late, due to time allocated to an additional independent check of the calculations.
- Accurate calculations protect the whole project, and we can likely recover the three days elsewhere in the permitting process.
- We can submit the permit package Thursday as planned without the structural sheets, or hold it and submit the complete package next Tuesday.
- I recommend holding it, because an incomplete package usually brings agency comment rounds and resubmittal fees, and each review can take a month or more.
- Please let me know which you prefer by Wednesday, so we have time to prepare Thursday's submittal if you choose that option.
- If I have not heard from you by then, I will hold the package and submit the complete package next Tuesday.
- Going forward, our team and the firm are building this additional check
More Delays Videos
Free script pack
Get the Free Delays Script Pack
The next conversation will not sound like this one. The free Delays pack gives you five more scripts for when the schedule slips and the client needs to hear it from you, each in friendly, neutral, and firm versions, so the right words are ready before you need them.
The pack arrives by email in a few minutes. After that, the weekly newsletter.
Your address is used only for the pack and the newsletter. No spam. Unsubscribe anytime.