Delays

Reporting a Delay to a Client With a Recovery Plan

Published September 22, 2026

How to Use a Script

Four steps:

  1. Watch the video once.
  2. Copy the script. Change the names, dates, and numbers to match your project.
  3. Say it out loud until it sounds like you. Use the practice sheet if the page has one.
  4. Use it in the real conversation, in the email or on the call.

The Script

Word for word, as said in the video. Copy it and change the names, dates, and numbers to match your project.

ScriptReporting a Delay to a Client With a Recovery Plan

Update on the curtain wall design. We found a coordination conflict between the HVAC routing and the facade support structure. This will delay the curtain wall drawings by one week.

Recovery plan.

  1. A. Absorb the week and adjust the glazing installation start date.
  2. B. Fast-track the HVAC rerouting and recover four days.

I recommend Option B. It keeps us closer to the original schedule with minimal cost impact. I need your decision by Thursday so we can brief the facade contractor.

Free script pack

Get the Free Delays Script Pack

The next conversation will not sound like this one. The free Delays pack gives you five more scripts for when the schedule slips and the client needs to hear it from you, each in friendly, neutral, and firm versions, so the right words are ready before you need them.

The pack arrives by email in a few minutes. After that, the weekly newsletter.

Your address is used only for the pack and the newsletter. No spam. Unsubscribe anytime.