Don't Wait Until Pour Day: Tell the Client About Weather Delays

Published November 17, 2026

How to Use a Script

Four steps:

  1. Watch the video once.
  2. Copy the script. Change the names, dates, and numbers to match your project.
  3. Say it out loud until it sounds like you. Use the practice sheet if the page has one.
  4. Use it in the real conversation, in the email or on the call.

The Script

Word for word, as said in the video. Copy it and change the names, dates, and numbers to match your project.

ScriptDon't Wait Until Pour Day: Tell the Client About Weather Delays

0:05

You're managing the footing pour for a new structure. Pour day is a week away. Heavy rain is forecast for pour day, and the concrete supplier can't pour in heavy rain, so the pour moves four days. The steel crew starts right after the concrete cures, so the delay moves their start too. You've checked the earliest dry pour window with the supplier, and you've confirmed the formwork and steel inspections remain on. You've also checked the float. What you do next decides whether the client hears it from you, or finds out on site.

0:39

The rain is not your doing, so you owe no apology. Give the client how far the pour moves, what moves with it, and a choice. Do it the moment the forecast changes, long before pour day. Write to the client directly. Look at this weak message first. We appreciate your patience. The weather may delay the pour. More news soon. If you wait for certainty, the client learns of it too late to plan.

1:08

Send this instead. Heavy rain is forecast for pour day, so the supplier cannot pour. The pour moves back four days. Option A. We move the steel crew start by the same four days. There is no added cost. The end date moves by up to four days. Option B. We aim to keep the end date, with a second steel crew so the steel work catches up after the pour. That adds cost. I recommend option A, because option B adds cost to hold a date that rain could move again. Please tell me your choice by Thursday, so I can confirm the pour date.

1:46

Remember to get the five free delay scripts and the free practice sheet. The links are in the description.

1:52

Build the message in this order. Facts. Options. Recommendation. Next step.

1:59

Give the facts first. Give the reason in one sentence, then say how far the pour moves.

2:06

Welcome to practice. Here, you repeat after me. Listen to each sentence. Then, in the pause, say it back out loud. Remember to say it out loud, not in your head. I will say every sentence two times, and after each one, you say it. Copy the sound and the rhythm, and try to match my voice. This is how your English starts to sound natural. Do not worry about mistakes. If you miss a word, keep going. The more you practice, the more conversational and natural your English will become. When an example ends, we say it all together. Need it slower? Tap the gear and set playback speed to 0.75. Ready? Let's begin.

3:40

Now say it all with me.

3:42

Heavy rain is forecast for pour day, so the supplier cannot pour. The pour moves back four days.

3:51

Second, offer two options, so the decision stays with the client. Option A moves the steel crew by the same four days. It costs nothing, and the end date moves by up to four days. Option B aims to keep the end date. A second steel crew lets the steel work catch up after the pour. The client pays for the second crew.

6:17

Now say it all with me.

6:19

Option A. We move the steel crew start by the same four days. There is no added cost. The end date moves by up to four days. Option B. We aim to keep the end date. We add a second steel crew. The steel work then catches up after the pour. That adds cost.

6:43

Third, say what you recommend right after the options. The reason is a fact about cost and risk. Option B only works if the weather holds, so the client could pay to protect a date that moves again.

7:34

Now say it all with me.

7:36

I recommend option A. Option B adds cost to hold a date that rain could move again.

7:43

Finally, ask which option they prefer, and give one deadline with its reason. The supplier needs a confirmed slot, so the client answers by Thursday. Keep that part a plain fact about the schedule.

8:24

Now say it all with me.

8:26

Please tell me your choice by Thursday, so I can confirm the pour date.

8:31

Now the client pushes back. They say, Can we pour anyway, and hope the rain stays away? Stay calm, and say this.

9:58

Now say it all with me.

10:00

I understand you want to keep the date. The supplier cannot pour in heavy rain, because rain can weaken the concrete. A dry day protects the foundation, and option A adds no cost.

Free script pack

Get the Free Delays Script Pack

The next conversation will not sound like this one. The free Delays pack gives you five more scripts for when the schedule slips and the client needs to hear it from you, each in friendly, neutral, and firm versions, so the right words are ready before you need them.

The pack arrives by email in a few minutes. After that, the weekly newsletter.

Your address is used only for the pack and the newsletter. No spam. Unsubscribe anytime.