Delays

Weather Delay: Do Not Wait for Certainty to Tell the Client

Published October 31, 2026

How to Use a Script

Four steps:

  1. Watch the video once.
  2. Copy the script. Change the names, dates, and numbers to match your project.
  3. Say it out loud until it sounds like you. Use the practice sheet if the page has one.
  4. Use it in the real conversation, in the email or on the call.

The Script

Word for word, as said in the video. Copy it and change the names, dates, and numbers to match your project.

ScriptWeather Delay: Do Not Wait for Certainty to Tell the Client

Avoid sending this. Thank you for your patience. The weather may delay the pour.

We will update you when we know more. That message holds the news until it is certain, so the client hears too late. Send this instead.

Rain is forecast for the day of the pour, so the supplier cannot pour. The pour moves back four days.

Option A. We move the steel crew start by the same four days. There is no added cost.

The end date moves by up to four days.

Option B. We keep the steel crew start date, with a second crew and a concrete pump so the pour can finish ahead of it. That adds cost.

I recommend option A, because option B adds cost to hold a date that rain could move again. Please tell me which you prefer by Thursday, so I can confirm the new pour date with the supplier by Friday. Tell the client when the forecast changes, with a date and a choice.

Free script pack

Get the Free Delays Script Pack

The next conversation will not sound like this one. The free Delays pack gives you five more scripts for when the schedule slips and the client needs to hear it from you, each in friendly, neutral, and firm versions, so the right words are ready before you need them.

The pack arrives by email in a few minutes. After that, the weekly newsletter.

Your address is used only for the pack and the newsletter. No spam. Unsubscribe anytime.